Sewerage scheme for Porvorim and its surrounding areas in Bardez Taluka – Goa.

 Jun, 20 - 2014   projects

Need of sewerage Treatment plant:

1)    Unsafe disposal of sewage into the river Mandovi.

2)    Rise water table during monsoon causing overflow of septic tank.

3)    The area being close to Panaji city has high housing demand which would generate problems of disposal of sewage.

4)    The area has great tourism potential hence situation in tourist season would be  bad due to high extraction  levels of water and more generation of waste.

Salient features:

1)    Name of the project: Sewerage scheme for Porvorim and its surrounding                                         areas in Bardez Taluka – Goa.

2)    State & District : Goa & North Goa

3)    Project area :

i) Pilerne
ii) Penha De Franca
iii) Reismagos
iv) Nerul
v) Socorro
vi) Salvador Do Mundo
vii) Pomburpa

4)Population:

As per 2001 census: 51443

Year

2011

2026

2041

Stages considered

Present

Intermediate

Ultimate

Projected population

67967

95561

134702

Rate of water supply (lpcd)

135

135

135

Water Supply requirement in MLD

9.18

12.90

18.08

Waste water at 80% of WS in MLD

7.34

10.32

14.55

Infiltration at 5% of Sewage

0.37

0.52

0.73

Total Sewage generated in MLD

7.71

10.84

15.28

 

 

 

 

 

5)Proposed Sewerage scheme: 3 nos. of sewerage district.

Sewerage District 1 Sewerage District 2 Sewerage District 3
Area Pilerne,Penha De Franca (part), Nerul & Reismagos Socorro Salvador Do Mundo, Penha De Franca (part) ,Pomburpa
Area in Sq km 23.69 12.50 18.87
Population year 2041 69640 29032 36032
Water supply requirement In MLD                                   9.4 3.92 4.86
Sewage generated at 80%WS in MLD 7.52 3.14 3.89
Infiltration at 5% of sewage .38 0.16 0.19
Total Sewage generated In MLD 7.89 3.30 4.09
STP with its capacity 1 No. of 8 MLD 1 No. of 3.3 MLD 1 No. of 4MLD
No. of Pumping Stations 10 Nos. 4 nos. 12 Nos.
Sewerage System proposed in Km 94.62 27.774 62.140
Treatment process proposed      Membrane Biological Reactor Membrane Biological Reactor Membrane Biological Reactor
Cost  of  the  project  in (Rs crores)

Rs  210.00 Crores

 

IV)Location of STP in the area under project consideration:

The topography of the project area is hilly area sloping towards river Mandovi, location of discharge of the treated sewerage from the intake of water works and the other utilities like land available, power facilities, road access and communication facilities etc. was considered to locate the sewage treatment plant.

The plants are proposed to be located at three places thus dividing the entire project area into 3 distinct sewage district to facilitate the proper use of the sewage treatment plant. The locations of the three plants are at

1)    Nerul Dhareshwar

2)    Salvador  Do Mundo

3)    Giri.

V) Total Expenditure of the project:

Details of Project Cost:

i)

Collection & conveyance :

Rs 135.79 Crores

ii)

Pumping Stations :

Rs 3.94 Crores

iii)

Pumping machineries :

Rs 4.53 Crores

iv)

Pumping mains

Rs 4.77 Crores

v)

3 Nos. of STP(total 14 MLD):

Rs 17.00 Crores

vi)

Miscellaneous

Rs 4.07 Crores

vii)

SCADA:

Rs 7.04 Crores

viii)

vii) Equipments and Vehicles:

Rs 5.00 Crores

ix)

Capacity Building:

Rs 5.40 Crores

x)

Disposal works

Rs 3.00 Crores

Net cost:

Rs 190.54 Crores

Escalation Charges at 7 %:

Rs 13.34 Crores

Net cost after escalation in crores:

Rs 203.88 Crores

Add 3% contingencies Net Rs.:

Rs 6.12 Crores

Total cost of the Project:

Rs 210.00 Crores

Vi) Project Implementation key milestones:

i)

Collection & conveyance :

July 2010 to March 2013

ii)

Sewage Pumping Station :

Oct 2010 to June 2014

iii)

Pumping machinery

June 2011 to March 2013

iv)

Pumping main:

July 2011 to March 2014

v)

STP(3 Nos.) :

July 2010 to June 2014

vi)

SCADA:

Jan 2012 to March 2013

vii)

Miscellaneous works:

Oct 2010 to June 2014

viii)

Vehicles & Equipments:

April 2012 to March 2013

ix)

Appointment of consultant:

Between 2009 to 2010

x)

Planning /Designing/Tender preparation:

2009 to 2010

 

Tender Invitation between periods of
Collection & Conveyance July 2010 to Sept 2010
Pumping Station Oct 2010 to Dec 2010
Pumping Machinery June 2011 to August 2011
Pumping Main July 2011 to Sept 2011
STP July 2010 to Sept 2010
SCADA Jan 2012 to August 2012
Miscellaneous Works Oct 2010 to Dec 2010
Vehicles &Equipments April 2012 to June 2012

xi)           Construction of work : Oct 2010 to March 2013

xii)         Installation & commissioning : January to March 2013

xiii)        Project Status : Provide list of approvals/clearances

Likely Impacts of the Project :

I) Clean Environment in Porvorim and its surrounding areas in Bardez Taluka – Goa.

II) Reduction in water borne diseases.

III) Improvements in the status of health.

IV) Protection to marine life as well as to safeguard pollution of human food chain.

v) Improvement in socio economical conditions by attracting more tourists.